Alpha Controls delivered a full BMS installation across Levels 7, 9 and 10 at 1 Stephen Street, London, working in partnership with System 5. The project covered trench heating controls, FCU networking, plant integration, and structured secondary containment throughout each floor.

Working in partnership with System 5, Alpha Controls delivered a comprehensive BMS installation across three floors of this Central London commercial office building. The scope encompassed trench heater controls, fan coil unit networking, plant system integration, and full secondary containment — all installed to a high standard and ready for commissioning handover.
Project Scope
The project required Alpha Controls to deliver a fully integrated BMS infrastructure across Levels 7, 9 and 10 of 1 Stephen Street. Each floor received its own dedicated BMS panel, installed within riser cupboards and connected throughout via structured containment and cable tray routes.
All works were carried out using podium access equipment with full PPE at all times. A dedicated on-site storage area was maintained throughout, with cable deliveries managed to keep the working environment clean, controlled, and safe.
Trench Heating & Zone Control
New 24V trench heater wiring and BMS control cabling were installed across eight zones per floor. Each zone comprised three trench heaters connected in series, complete with two actuators per zone — providing accurate zonal control and efficient heating distribution across perimeter areas.
Trench Heating Summary
- 8 zones per floor across Levels 7, 9 and 10
- 3 trench heaters per zone, wired in series
- 2 actuators per zone for precise flow control
- New 24V BMS control cabling installed throughout
Fan Coil Units & Network Installation
Across all three floors, Alpha Controls installed BMS network cabling for approximately 20 FCUs per floor, routing and terminating all connections back to local panels within the riser cupboards. In addition, condensate pumps were installed and connected to each FCU to support drainage and reliable system operation.
- ~60 FCUs networked across Levels 7, 9 and 10
- All cables routed and terminated to local riser panels
- Condensate pumps installed and connected to each FCU


Plant & System Integration
Key plant systems were integrated into the BMS across all three floors, providing centralised monitoring and control of building environment and safety systems. Each floor received its own dedicated BMS panel, mounted within the riser cupboard and connected via structured containment and tray routes.
- Air Handling Units (AHUs) integrated and connected to BMS
- Leak detection systems installed and wired to local panels
- Dedicated BMS panel per floor, riser-mounted on Levels 7, 9 and 10

Containment & Cable Management
Secondary containment was installed using steel conduit systems, including bending, threading, and installation using stocks and dies. Cables were run within underfloor tray systems around the building perimeter, neatly dressed and secured using cable ties throughout.
This structured approach to containment ensures long-term accessibility for maintenance engineers, provides physical protection to control and signal cables, and maintains a clean, professional installation throughout each floor.
Outcome
The installation delivered a fully integrated BMS infrastructure across all three floors, supporting heating control, environmental monitoring, and plant integration. The project was completed to a high standard of workmanship — ensuring reliability, accessibility, and full readiness for commissioning.
- Fully integrated BMS across Levels 7, 9 and 10
- Precise trench heating control across 24 zones total
- ~60 FCUs networked and ready for commissioning
- AHU and leak detection systems fully integrated
- Clean, structured containment with steel conduit and underfloor tray
Conclusion
The 1 Stephen Street project demonstrates Alpha Controls' ability to deliver multi-floor BMS installations within a live construction environment, coordinating across trades and working to a precise programme. Delivered in partnership with System 5, the result is a reliable, well-structured BMS infrastructure ready for full commissioning and long-term operation.
Explore Our BMS Installation ServicesTechnical Specifications
Heating Controls
- 24V Trench Heater BMS Wiring
- 8 Zones per Floor
- 3 Heaters per Zone (Series)
- 2 Actuators per Zone
FCU Networking
- ~20 FCUs per Floor
- BMS Network Cabling
- Condensate Pump Installation
- Riser Panel Termination
Plant Integration
- Air Handling Units (AHUs)
- Leak Detection Systems
- Dedicated BMS Panel per Floor
- Riser-Mounted Panels
Project Details
- Client: System 5
- Floors: Levels 7, 9 & 10
- Location: Fitzrovia, London W1
- Sector: Commercial Office
Ready to Transform Your Building's Performance?
Whether it's a retrofit, upgrade, or full new-build installation, Alpha Controls delivers professional BMS installations that optimise comfort, performance, and energy efficiency across every building type.